How to Audit a Chinese Machine Shop: On the Floor
By CHX Metal Engineering Team · Published 2026-11-20
An audit day checks what a checklist cannot: the machine park counted and running, calibration stickers on gauges, work-in-progress on the line, and documents pulled live. Our Shenzhen plant has machined since 2013 across 220 machines and holds ±0.005 mm on critical features; customers audit before a first order.
Skip the meeting room. Start at the metrology room
Most factory visits run the same way: a slide deck, a tour past the newest machines, tea, and a farewell. It feels like an audit and proves almost nothing. The order matters more than the length. Walk to the metrology room first, before anyone has had time to tidy it, and ask to see the gauge cabinet. A shop that measures well at eight in the morning usually machines well all day; a shop that needs an hour to prepare the measuring room has told you something.
A desk checklist - ownership, business licence, certification scope, references - is still worth doing, and it belongs before the trip. But every item on it verifies a claim. The trip is the only stage where claims turn into evidence, and the difference between the two is what the rest of this page covers. The desk half is laid out in the 10-point vetting checklist.
Count the machines that are actually running
Every supplier hands over an equipment list, and the list is always impressive. The audit question is simple: walk the floor during a working shift and count what is turning. Not what is plugged in - what is cutting, with chips coming off and a setter nearby. A park of 220 machines means little if a third sit under plastic covers; a park of 60 running flat out with an order board on the wall may be the honest match for your volume.
Three details carry more information than the list itself. First, the work-in-progress: clamps holding five different customers' parts is a healthy sign; every fixture holding the same part shape means one large order is about to finish, and your batch will land on an empty schedule with no process memory. Second, the Swiss-type cells - if your parts are small and round, watch whether the bar feeders are loaded and running, because Swiss-type capacity is the first thing small-part buyers overestimate. Third, the scrap bins. A bin with a few clearly labelled grey parts is a shop that catches its own mistakes; an empty bin beside a full rework bench is a shop that hides them.
The metrology room earns the second hour
Bring one finished part from a comparable job - or ask the shop to pull a part currently in production - and ask for it to be measured while you watch. What matters is less the number than the routine: which gauge they reach for first, whether the CMM program matches the drawing datums, whether the micrometer in use has a calibration sticker with a date that has not passed. A sticker dated three years ago on the gauge they actually use says the certificate drawer is decoration.
Tolerance claims belong here too. A shop that quotes ±0.005 mm on critical features should be able to show you how that number was verified - a CMM report, a gauge repeatability check, the environment of the measuring room. Looser dimensions are normally handled to ISO 2768-m, and asking how the shop proves a mid-tolerance feature is a fairer test of the quality system than reading the certificate. The reporting that should follow a first order is described on the inspection and FAI reporting page.
Pull the documents live, not by email afterwards
Anything you request after the visit arrives filtered. Ask during the walk, and watch how fast it appears. The short list: the quality certificate itself, with scope and certificate number - ours is ISO 9001:2015 and ISO 14001:2015 - plus the calibration register for the gauges you just saw, a first-article report from a real job with names removed, and a material certificate matching a heat number to a bar in the stock rack.
The heat-number test is the one most audits skip, and it is the cheapest. Pick a length of stock at random, ask for its certificate, and check the heat number stamped or tagged on the material matches the paper. Traceability that works on an unannounced bar works on your parts. Traceability that requires a phone call and ten minutes of searching works differently.
Three questions that expose padded capacity
Capacity claims collapse on arithmetic. Ask what a typical part of yours would cost in machine hours, then divide the total available hours by it - the answer either fits the headcount on the floor during your visit or it does not. Ask how many shifts run, then check the second-shift story against the shift board and the canteen. Ask which machines your parts would run on, then walk back to those machines and ask the setter what he last cut on that one. A setter who answers with a part name and a material is running that machine; a setter who gestures at the sales manager was placed there for the tour.
Score the visit the same evening, while details are fresh, and write down the two or three claims you could not verify - those become the trial order's checkpoints. Most buyers then run a small first order before committing a program; how to structure that step is on the supplier selection page. An audit that ends without a written list of unverified claims was a tour.
What we show on an audit day
Buyers visit our plant in Shajing, Bao'an District before a first order, and the agenda is the one above: metrology room first, machine park during a working shift, documents pulled on the spot. The floor runs 220 machines - 100 machining centres with 30 of them 3+2, 50 CNC lathes, and 70 Tsugami Swiss-type units - with 100+ staff and monthly capacity of 5 million pieces, machining since 2013. Whether a visit is possible or not, the same evidence is available by video: a live walk of the floor on your call, gauges shown with their calibration stickers, and a first-article report sample before you commit.
| Field | CHX Metal |
|---|---|
| Location | Shajing, Bao'an, Shenzhen, China - 5,000 m² plant, 100+ staff, machining since 2013 |
| Equipment | 220 machines: 100 machining centres (30 of them 3+2), 50 CNC lathes, 70 Tsugami Swiss-type lathes |
| Tolerances | ±0.005 mm on critical features; unmarked dimensions to ISO 2768-m; CMM and optical measurement |
| MOQ | 1 piece |
| Lead times | Prototypes 3–7 days; production 7–15 days; capacity to 5 million pieces per month |
| Materials | 6061/7075 aluminium, 303/304/316L stainless, TC4 titanium, H59 brass, engineering plastics; ISO 9001:2015 and ISO 14001:2015 certified |
| Quality | First-article reports, material certificates with heat-number traceability, calibration register available for customer audits |
| Shipping | EXW Shenzhen only - we are happy to recommend reliable freight forwarders. |
Machining capacity behind this article
- Equipment: 220 machines — 100 machining centres (30 of them 3+2), 50 CNC lathes, 70 Tsugami Swiss-type lathes.
- Tolerance: ±0.005 mm on critical features; anything unmarked defaults to ISO 2768-m.
- Volume: up to 5 million pieces a month; prototyping 3–7 days, production 7–15 days.
- Materials: 6061/7075 aluminium, 303/304/316 stainless, H59 brass, copper, TC4 titanium, carbon steel.
- Footprint: 5,000 m² in Shajing, Bao'an, Shenzhen; 100+ staff; founded 2013.
- Terms: EXW Shenzhen only — we are happy to recommend reliable freight forwarders.
Address: Building B, 3rd Floor, Haosan Maozhoushan Industrial Zone, Buyong Community, Shajing Street, Bao'an District, Shenzhen | Tel: +86-755-27427365 | Email: mc@chxmetal.com
Frequently asked questions
How is an on-site audit different from a supplier vetting checklist?
A checklist verifies claims from your desk: licence, certification, references, equipment list. An audit day verifies evidence: machines counted running during a working shift, calibration stickers on the gauges actually in use, work-in-progress from several customers, and documents pulled live rather than emailed later. Both stages matter, and the checklist belongs first - the trip is where the claims get tested.
What should I look at first when I walk into the factory?
The metrology room, before the meeting room and before anyone tidies it. Check which gauge they reach for first, whether its calibration sticker is current, and ask for a live measurement of a part comparable to yours. A measuring room that is ready at eight in the morning says more about a shop than any slide deck.
How can I verify a supplier's machine count and capacity on site?
Walk the floor during a working shift and count machines actually cutting, then ask which machines your parts would run on and question the setter at those machines about what he last cut there. Cross-check shift claims against the shift board, and do the hours arithmetic: total machine hours divided by your part's cycle time either fits the headcount you see or it does not.
Which documents should I ask for during the visit itself?
Four, pulled on the spot: the quality certificate with scope and number, the calibration register for the gauges you just saw, a first-article report from a real job with names removed, and a material certificate matching a randomly chosen bar's heat number. Anything a supplier offers to email after the visit has been filtered first.
Can the audit be done remotely if travel is not possible?
Largely, yes. A live video walk of the floor during a working shift, gauges shown with their calibration stickers, the heat-number test done on camera, and a first-article report sample sent before commitment cover most of the evidence an in-person day would gather. What video cannot replace is the informal checks - the scrap bin, the canteen, the setter's answer - so we recommend an on-site visit before a large program.
Send your drawings for a DFM review and a quotation